Marquette
Interchange: DOT tracking steel prices
Also
on this page:
Courthouse
annex, "pit parking"
to go?
Fixing
roads provides more jobs than building them,
study says.
$25,000
per meeting "typical," DOT says.
|
April
19 -- The Wisconsin Department of Transportation
is keeping an eye on the skyrocketing cost of
steel, but how those rising prices will affect
the Marquette Interchange reconstruction project
is not yet known, according to a DOT official.
Gov.
Doyle has promised to keep the cost of the Interchange
under $810 million, but if steel price trends
continue, that promise will be difficult to keep.
Steel
will be a major component of the new Interchange.
A
representative of the American Road & Transportation
Builders Association (ARTBA) told the U.S. House
of Representatives last month that the price of
steel used in highways and bridges jumped 30%
to 80% since the end of last year.
“Price
changes are one of the risks we take to be in
this business,” said Pat Loftus, who was
representing the American Road & Transportation
Builders Association’s Materials & Services
Division. “The steel price increases of
recent months, however, were far outside normal
fluctuations, were totally unexpected and will
have a very disruptive impact on individual highway
and bridge construction projects in the very near
future. The convergence of these factors has resulted
in a ‘Perfect Storm’.”
WisDOT
spokeswoman Pat Schmitt said that industry analysts
"are predicting that the price will continue
to rise in the short term and stabilize at lower
levels later in the year. Current indicators suggest
that the price will stabilize at a higher level
than historical prices, but no one has a good
prediction of what that level will be."
Schmitt said major steel-related contracts for
the Marquette won't be let until July and August
of 2005.
"It
is too early to estimate what impact the steel
prices may have on the total project," she
wrote. "The Department is monitoring the
price situation and will make adjustments as needed
to deal with steel prices."
Courthouse
annex, "pit" parking
to go?
600 Downtown spaces at risk
April
4 -- As many as 600 Downtown
parking spaces could be lost due to the Marquette
Interchange reconstruction and concerns about
possible terrorist attacks, according to County
Supervisor Lynne DeBruin.
The
Courthouse annex, which bridges I-43, may have
to be taken down for the Marquette project, she
said. And county officials do not know when --
if ever -- the federal government will allow drivers
to park under the Interchange after the project
is finished.
"There
apparently is quit a bit of concern that we could
lose both," she said.
Rumors
were circulating in the courthouse that the Department
of Homeland Security would prohibit parking under
the new Interchange because of concerns that terrorists
would park bomb-laden cars there to blow up the
freeway crossroads.
"The
rumor you heard is potentially true," DeBruin
said.
Jurors
and county workers park under the freeway in an
area known as the "pit." The county
already is beginning to prohibit parking in some
spaces there because of the reconstruction project.
The lot, with about 200 spaces, likely will be
completely closed by January for the duration
of the reconstruction effort, DeBruin said. It
probably won't be known for a few years if the
feds will allow parking to resume there.

DeBruin
In
addition, she said, "the entire annex may
not be able to withstand the construction so close
to its own piling system. "The annex may
have to be torn down."
Marquette
Interchange plans call for the State Department
of Transportation to acquire 2,575 square feet
of annex property for new freeway right-of-way,
according to DOT documents. The Interchange plans
did not include tearing down the structure.
The
Southeastern Wisconsin Regional Planning Commission,
however, anticipated the annex would have to be
torn down if freeways are widened, as the commission
is recommending. SEWRPC said the value of the
annex was about $15.7 million in 2000 dollars.
Fixing
roads provides more jobs than building them, study
says
April
4 -- Maintaining and repairing roads
creates more new jobs than expanding or building
roads does, according to a new report.
"Fix
it first" projects, such as resurfacing,
rehabilitating, or replacing bridges and roads
creates just over 47,0000 jobs for every $1.25
billion spent.
Spending
$1.25 billion on building new roads creates 43,200
jobs, according to the Surface Transportation
Policy Project.
"An
interesting finding of STPP's analysis...is that
'environment-related' transportation projects,
which include wetland mitigation, noise barrier
construction, and air quality programs, generate
the highest number of jobs," the organization
said in a summary of its findings.
Environmental
projects create 51,200 jobs for every $1.25 billion
spent. Safety projects create 48,300 jobs per
$1.25 billion spent.
"Investments
in public transportation produce almost nine percent
more jobs per dollar spent than road and bridge
repair and maintenance projects, and nearly 19
percent more jobs than new road or bridge projects,"
STPP said.
Environmental
projects create 51,300 new jobs for every $1.25
billion spent.
STPP
is a 501(c)(3) non-profit organization funded
by individual donations and a range of national
and regional foundations including Agua Foundation,
the Fannie Mae Foundation, the Ford Foundation,
the Heinz Foundation, the Hewlett Foundation,
the Robert Wood Johnson Foundation, the Joyce
Foundation, the James Irvine Foundation, the Kirsch
Foundation, the MacArthur Foundation, the McKenna
Foundation, the David & Lucille Packard Foundation,
the William Penn Foundation, the Pittsburgh Foundation,
the Prince Charitable Trust, the Rausch Foundation,
the Rockefeller Foundation, and the Surdna Foundation.

$25,000
payments for meeting "typical," DOT
says
March
20 -- The $25,000 that DOT offered to
pay consultants to prepare and a attend a single
public information is "typical," according
to DOT secretary Frank Busalacchi.
The
webteam reported recently that CH2M Hill and HNTB,
consultants on the Marquette Interchange project,
were to be paid about $26,000 for helping to prepare
for and attending a single public information
meeting.
"While
this figure may seem high, the effort involves
a great many activities, including creating and
distributing newsletters, placing advertisements
in newspapers, and preparing handout materials,"
Busalacchi wrote in a letter to Ald. Michael J.
Murphy.
Busalacchi
was responding to Murphy's inquiry about the fee.
CHM2
Hill, at the time the no-bid main contractor for
Marquette Interchange design study, was offered
$10,946.28 to participate in a fourth public informational
meeting, according to a 2002 contract amendment
obtained by the webteam through an open records
request.
HNTB,
then a subcontractor to CH2M Hill, was to be paid
$15,852.64 to help prepare and conduct the public
information session.
The
written offer that DOT extended did not include
any specific tasks the firms were to perform for
the money.
Busalacchi
said in his letter that costs associated with
public meetings "can be significant."
"For
example, we plan to mail nearly 6,000 postcards
to promte the upcoming March 24th public information
meeting on the Marquette Interchange project,"
he wrote. "Advertising alone can be expensive.
It costs about $1,000 to place a single weekday
ad in the Milwaukee Journal Sentinel. We also
place advertisements in minority and neighborhood
newspapers."
Busalacchi
did not say in his letter whether funding for
those types of things was to come from the CH2M
Hill or HNTB payments.
"In
addition to these costs, there is the cost of
consultant time to prepare for and staff the public
meeting," he wrote. "Several consultant
staff are usually available to the public during
a public information meeting to help answer questions
and address concerns."
The
amount CH2M Hill was to receive for attending
the hearing was enough to pay for more than 109
hours -- 13.7 work days -- of labor by people
earning $100 an hour.
"There
may also be costs for equipment, translators,
parking or other accommodations at the meeting
site," Busalacchi wrote.
At
the time the $26,000 offer was made, DOT the public
meeting it referred to was unscheduled and the
ancillary costs unknown.
"One
final note," Busalacchi wrote, "the
costs for the public information meeting you referred
to were estimates IF a fourth public meeting would
was authorized under the consultant. This option
was not authorized and the funds will not be expended."
Contrary
to Busalacchi's statement, the amounts in the
contract are clearly not estimates.
The
webteam has asked DOT how much its consultants
will be paid for the March 24 public information
meeting.
Meeting
details, as outlined on the DOT's Marquette Interchange
web site, can be found below.
When:
March 24, 2004
3 to 8 p.m.
Formal presentation at 5:30 p.m.
Where:
Milwaukee County War Memorial
750 N. Lincoln Memorial Drive
Milwaukee, WI 53202
Parking is available on the street
and in the parking structure west
of the building.
Topics to be discussed include:
• Clybourn Street advanced work
• General information brochure
• DBE information