Highway project costs soar

Project
Cost Estimate(millions)
Change
 
Feb. 2006
Aug. 2006
$ (millions)
%
US 12 Sauk City - Middleton
134.6
136.4
1.8
1
US 12 Lake Delton-Sauk City
107.7
155.0
47.3
44
STH 26 Janesville-Watertown
265.0
342.4
77.4
29
STH 81/STH 213 Beloit Bypass
7.1
7.8
0.7
10
USH 151 Dickeyville -- Belmont
95.6
99.4
3.8
4
USH 14 Viroqua-Westby
43.3
51.6
8.3
19
USH 18 Prairie du Chien - STH 60
23.9
24.9
1.0
4
USH 53 LaCrosse Corridor
104.8
118.1
13.3
13
STH 11 Burlington Bypass
115.3
144.9
29.6
26
USH 12 Whitewater Bypass
36.7
38.3
1.6
4
STH 16 Oconomowoc Bypass
52.5
53.0
0.5
1
USH 151 Waupun - Fond du Lac
118.9
127.8
8.9
7
USH 151 Fond du Lac Bypass
45.3
48.6
3.3
7
USH 10 - USH 45
97.2
97.3
0.1
0
STH 23 STH 67 - USH 41
95.6
95.6
0
0
USH 41 Oconto - Peshtigo
146.3
170.8
24.5
17
USH 41 STH 26 -- Breezewood La.
292.2
337.5
45.3
16
USH 41 DePere-Saumico
364.7
416.5
51.8
14
STH 57 Dyckesville - Sturgeon Bay
96.7
96.7
0
0
USH 45 (STH 110 Project) USH 41 - STH 116
42.7
43.1
0.4
1
USH 141 STH 22 - STH 64
64.9
64.9
0
0
USH 10 Marshfield - Stevens Point
192.0
221.0
29
15
USH 10 Stevens Point - Waupaca
82.8
82.9
.1
0
I39 / USH 51 Wausau Corridor
249.1
279.3
30.2
12
STH 29 I94 - Chippewa Falls
147.6
147.6
0
0
USH 53 Eau Claire Bypass
173.9
176.3
2.4
1
STH 64 Houlton - New Richmond
113.2
116.5
3.3
3

 

 